Duyen Hai Phase I Project Unit 1 Sign PAC Agreement

On 6 January 2016, General Manager of the 5th Project Division Mr. Ren Yu signed PAC Agreement with the Vietnam client. The agreement clarifies that 4 January 2016 is the synchronization date, completion date, and valid date for warranty period for unit 1. It also symbolizes the date when unit 1 and utility system operation being comprehensively handed over to the client. Duyen Hai Project Unit 1 has since then being successfully handed over to the client after 5 years’ unremitting efforts.